PSM-I · Question #148
PSM-I Question #148: Real Exam Question with Answer & Explanation
Sign in or unlock PSM-I to reveal the answer and full explanation for question #148. The question stem and answer options stay visible for context.
Question
Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach. A good way to continue is:
Options
- AThe Development Team makes sure that all of the selected scope per Sprint is as "Done" as
- BAdd enough people to the Development Team for the deadline to be made.
- CThe opportunity to inspect and adapt is lost. Opaqueness has replaced transparency.
- DThe Development Team should remind Marian to find funding for enough Release Sprints in
Unlock PSM-I to see the answer
You've previewed enough free PSM-I questions. Unlock PSM-I for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.