PSM-I Question #112: Real Exam Question with Answer & Explanation

The correct answer is B: By the Development Team deciding what work to do in a Sprint.. Scrum promotes self-organization through: (B) the Development Team deciding what work to do in a Sprint (they pull items from the Product Backlog themselves during Sprint Planning), (D) removing titles for Development Team members (everyone is simply a 'Developer,' eliminating hi

Submitted by katya_ua· Apr 18, 2026Developing People and Teams

Question

What are three ways Scrum promotes self-organization? (Choose three.)

Options

  • ABy not allowing documentation.
  • BBy the Development Team deciding what work to do in a Sprint.
  • CBy preventing stakeholders from entering the development room.
  • DBy removing titles for Development Team members.
  • EBy being a lightweight framework.

Explanation

Scrum promotes self-organization through: (B) the Development Team deciding what work to do in a Sprint (they pull items from the Product Backlog themselves during Sprint Planning), (D) removing titles for Development Team members (everyone is simply a 'Developer,' eliminating hierarchy), and (E) being a lightweight framework (minimal rules give teams space to self-organize around their work). Option A is false - Scrum does not prohibit documentation. Option C is also false - Scrum does not isolate teams from stakeholders; Sprint Reviews specifically invite them.

Topics

#Self-organization#Development Team#Scrum Framework#Team Autonomy