PSM-I · Question #111
Which two things should the Development Team do during the first Sprint? (Choose two.)
The correct answer is C. Develop at least one piece of functionality. E. Create an increment of potentially releasable software. During the first Sprint, the Development Team should (C) develop at least one piece of functionality and (E) create an increment of potentially releasable software. Scrum does not front-load planning or documentation - there is no 'Sprint 0' for architecture or requirements…
Question
Which two things should the Development Team do during the first Sprint? (Choose two.)
Options
- AMake up a plan for the rest of the project.
- BAnalyze, describe, and document the requirements for the subsequent Sprints.
- CDevelop at least one piece of functionality.
- DAnalyze, design, and describe the complete architecture and infrastructure.
- ECreate an increment of potentially releasable software.
How the community answered
(49 responses)- A8% (4)
- B4% (2)
- C69% (34)
- D18% (9)
Explanation
During the first Sprint, the Development Team should (C) develop at least one piece of functionality and (E) create an increment of potentially releasable software. Scrum does not front-load planning or documentation - there is no 'Sprint 0' for architecture or requirements analysis. Sprints are meant to produce working software from day one. Option A describes waterfall-style planning, and options B and D describe big upfront design, both of which contradict Scrum's empirical and iterative approach.
Topics