What is the input to the Sprint Planning? Select four.

The correct answer is B. Past performance of the Development Team C. The latest product Increment D. Projected capacity of the Development Team during the Sprint E. The Product Backlog. The Scrum Guide explicitly identifies four inputs to Sprint Planning: (E) The Product Backlog - the ordered source of potential work; (C) The latest product Increment - represents the current state of the product and what has been built so far; (D) Projected capacity of the…

Submitted by lars.no· Apr 18, 2026Scrum Framework

Question

What is the input to the Sprint Planning? Select four.

Options

  • AFeedback from the Organization CEO
  • BPast performance of the Development Team
  • CThe latest product Increment
  • DProjected capacity of the Development Team during the Sprint
  • EThe Product Backlog
  • FFeedback from the Key Stakeholders

How the community answered

(44 responses)
  • A
    7% (3)
  • B
    89% (39)
  • F
    5% (2)

Explanation

The Scrum Guide explicitly identifies four inputs to Sprint Planning: (E) The Product Backlog - the ordered source of potential work; (C) The latest product Increment - represents the current state of the product and what has been built so far; (D) Projected capacity of the Development Team - accounts for team availability, vacations, and other commitments during the Sprint; and (B) Past performance of the Development Team - their historical velocity and throughput informs how much work is realistically achievable. CEO feedback (A) and key stakeholder feedback (F) are not formal Sprint Planning inputs defined by Scrum - stakeholder input is channeled through the Product Owner's ongoing management of the Product Backlog, not directly into Sprint Planning.

Topics

#Sprint Planning#Scrum Events#Scrum Inputs#Product Backlog