PSM-I · Question #104
Who is responsible for tracking the total work remaining in the Sprint Backlog to project the likelihood of achieving the Sprint Goal?
The correct answer is B. The Development Team. According to the Scrum Guide, the Development Team is responsible for tracking the total work remaining in the Sprint Backlog. They update this at least at every Daily Scrum to project the likelihood of achieving the Sprint Goal. This is part of their self-managing nature…
Question
Who is responsible for tracking the total work remaining in the Sprint Backlog to project the likelihood of achieving the Sprint Goal?
Options
- AThe Product Owner
- BThe Development Team
- CThe Product Owner and the Development Team
- DThe Scrum Master
- EThe Scrum Team
How the community answered
(35 responses)- B94% (33)
- D3% (1)
- E3% (1)
Explanation
According to the Scrum Guide, the Development Team is responsible for tracking the total work remaining in the Sprint Backlog. They update this at least at every Daily Scrum to project the likelihood of achieving the Sprint Goal. This is part of their self-managing nature - they own their plan and monitor their own progress. The Product Owner owns the Product Backlog, not the Sprint Backlog, and the Scrum Master serves the team without directing their work.