Scrum
PSD · Question #85
When might a sprint be cancelled?
The correct answer is D. When the sprint goal becomes obsolete. The product owner can cancel the sprint if the sprint goal becomes obsolete. This is a very rare event. It can happen when a company losing a client or the client decides to take a completely
Applying Scrum
Question
When might a sprint be cancelled?
Options
- AWhen the developers feel they aren't ready
- BWhen the project manager decides this.
- CNever, the sprint must always be finished.
- DWhen the sprint goal becomes obsolete
How the community answered
(43 responses)- B2% (1)
- C5% (2)
- D93% (40)
Explanation
The product owner can cancel the sprint if the sprint goal becomes obsolete. This is a very rare event. It can happen when a company losing a client or the client decides to take a completely
Topics
#Sprint cancellation#Sprint goal#Scrum events
Community Discussion