PSD · Question #80
How much time will there be after a sprint before the next one starts?
The correct answer is C. None, a new sprint starts immediately after the end of the previous one. The scrum guide says: "A new Sprint starts immediately after the conclusion of the previous
Applying Scrum
Question
How much time will there be after a sprint before the next one starts?
Options
- AEnough to deploy the increment and update the product backlog based on the outcome of the
- BEnough to clean up lingering definition of done points
- CNone, a new sprint starts immediately after the end of the previous one
- DAt most a week for a one-month sprint
How the community answered
(28 responses)- A4% (1)
- C93% (26)
- D4% (1)
Explanation
The scrum guide says: "A new Sprint starts immediately after the conclusion of the previous
Topics
#sprint cadence#continuous delivery#sprint transition