Scrum
PSD · Question #74
The product owner determines how many product backlog items the developers select for the sprint in the sprint planning.
The correct answer is F. False. It is false, the developers select the items, because they will have to commit to it.
Applying Scrum
Question
The product owner determines how many product backlog items the developers select for the sprint in the sprint planning.
Options
- AFalse, the scrum master does that
- BTrue
- CTrue, in line with what was promised to the stakeholders
- DTrue, if the developers have enough capacity
- EFalse, the project manager does that
- FFalse
How the community answered
(23 responses)- C9% (2)
- E4% (1)
- F87% (20)
Explanation
It is false, the developers select the items, because they will have to commit to it.
Topics
#sprint planning#product owner authority#developers#self-management