PSD · Question #74

PSD Question #74: Real Exam Question with Answer & Explanation

The correct answer is F. False. It is false, the developers select the items, because they will have to commit to it.

Question

The product owner determines how many product backlog items the developers select for the sprint in the sprint planning.

Options

  • AFalse, the scrum master does that
  • BTrue
  • CTrue, in line with what was promised to the stakeholders
  • DTrue, if the developers have enough capacity
  • EFalse, the project manager does that
  • FFalse

Explanation

It is false, the developers select the items, because they will have to commit to it.