Which statement best describes the sprint review?

The correct answer is A. It is a chance for inspecting the outcome of a sprint and determining the next steps C. It is a demo of the work that was done. The scrum guide says: "The purpose of the Sprint Review is to inspect the outcome of the Sprint and determine future adaptations. "

Applying Scrum

Question

Which statement best describes the sprint review?

Options

  • AIt is a chance for inspecting the outcome of a sprint and determining the next steps
  • BIt is a mechanism to control the work of the developers
  • CIt is a demo of the work that was done

How the community answered

(52 responses)
  • A
    92% (48)
  • B
    8% (4)

Explanation

The scrum guide says: "The purpose of the Sprint Review is to inspect the outcome of the Sprint and determine future adaptations. "