Scrum
PSD · Question #7
Which of the following is required by Scrum? (choose the best answer)
The correct answer is A. Sprint Retrospective. Scrum mandates the Sprint Retrospective to inspect and adapt. Other practices, such as burndown charts and release planning, are tools and techniques but are not required by Scrum.
Applying Scrum
Question
Which of the following is required by Scrum? (choose the best answer)
Options
- ASprint Retrospective
- BDevelopers must stand up at the Daily Scrum.
- CSprint Burndown Chart.
- DRelease Planning.
- EAll of the above.
How the community answered
(30 responses)- A90% (27)
- C7% (2)
- E3% (1)
Explanation
Scrum mandates the Sprint Retrospective to inspect and adapt. Other practices, such as burndown charts and release planning, are tools and techniques but are not required by Scrum.
Topics
#Scrum events#Sprint Retrospective#Scrum requirements#Daily Scrum
Community Discussion
No community discussion yet for this question.