Scrum
PSD · Question #7
PSD Question #7: Real Exam Question with Answer & Explanation
The correct answer is A. Sprint Retrospective. Scrum mandates the Sprint Retrospective to inspect and adapt. Other practices, such as burndown charts and release planning, are tools and techniques but are not required by Scrum.
Question
Which of the following is required by Scrum? (choose the best answer)
Options
- ASprint Retrospective
- BDevelopers must stand up at the Daily Scrum.
- CSprint Burndown Chart.
- DRelease Planning.
- EAll of the above.
Explanation
Scrum mandates the Sprint Retrospective to inspect and adapt. Other practices, such as burndown charts and release planning, are tools and techniques but are not required by Scrum.
Community Discussion
No community discussion yet for this question.