Scrum
PSD · Question #55
What is the commitment for the sprint backlog?
The correct answer is B. Sprint goal. If you are not sure, please review the section scrum artifacts in the scrum guide.
Applying Scrum
Question
What is the commitment for the sprint backlog?
Options
- ADefinition of done
- BSprint goal
- CSprint planning outcome
- DProduct goal
How the community answered
(24 responses)- A4% (1)
- B92% (22)
- D4% (1)
Explanation
If you are not sure, please review the section scrum artifacts in the scrum guide.
Topics
#sprint backlog#sprint goal#Scrum commitments#sprint artifacts
Community Discussion
No community discussion yet for this question.