PSD · Question #55

What is the commitment for the sprint backlog?

The correct answer is B. Sprint goal. If you are not sure, please review the section scrum artifacts in the scrum guide.

Applying Scrum

Question

What is the commitment for the sprint backlog?

Options

  • ADefinition of done
  • BSprint goal
  • CSprint planning outcome
  • DProduct goal

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    92% (22)
  • D
    4% (1)

Explanation

If you are not sure, please review the section scrum artifacts in the scrum guide.

Topics

#sprint backlog#sprint goal#Scrum commitments#sprint artifacts