PSD · Question #48

When are testers and QA experts ideally included in the project?

The correct answer is B. From the beginning and throughout the sprints, but let's call them developers. Testing is an ongoing process, this is done by the developers. Developers can be specialized in testing. Please mind that the word developer means something else in the scrum context.

Applying Scrum

Question

When are testers and QA experts ideally included in the project?

Options

  • AAfter every sprint review
  • BFrom the beginning and throughout the sprints, but let's call them developers
  • CWhen the developers are done
  • DWhen the product is complete

How the community answered

(72 responses)
  • A
    3% (2)
  • B
    86% (62)
  • C
    8% (6)
  • D
    3% (2)

Explanation

Testing is an ongoing process, this is done by the developers. Developers can be specialized in testing. Please mind that the word developer means something else in the scrum context.

Topics

#QA integration#cross-functional team#testing roles#Scrum team