Scrum
PSD · Question #24
PSD Question #24: Real Exam Question with Answer & Explanation
The correct answer is A. True. A Sprint can be canceled if the Sprint Goal becomes obsolete, as stated in the Scrum Guide. This decision is made by the Product Owner, and it emphasizes Scrum's focus on delivering value.
Question
True or False: A Sprint can be canceled before the timebox ends.
Options
- ATrue
- BFalse
Explanation
A Sprint can be canceled if the Sprint Goal becomes obsolete, as stated in the Scrum Guide. This decision is made by the Product Owner, and it emphasizes Scrum's focus on delivering value.
Community Discussion