True or False: A Sprint can be canceled before the timebox ends.
The correct answer is A. True. A Sprint can be canceled if the Sprint Goal becomes obsolete, as stated in the Scrum Guide. This decision is made by the Product Owner, and it emphasizes Scrum's focus on delivering value.
Applying Scrum
Question
True or False: A Sprint can be canceled before the timebox ends.
Options
- ATrue
- BFalse
How the community answered
(27 responses)- A89% (24)
- B11% (3)
Explanation
A Sprint can be canceled if the Sprint Goal becomes obsolete, as stated in the Scrum Guide. This decision is made by the Product Owner, and it emphasizes Scrum's focus on delivering value.
Topics
#Sprint cancellation#Sprint timebox#Product Owner authority