Based on "Sprint 7 Burn-Down Chart," would you do anything different in Sprint 8? (choose the best two answers)

The correct answer is A. The Developers may forecast less overall work in Sprint 8. F. The Developers put incomplete Product Backlog items back into the Product Backlog for re-. If a burn-down chart shows issues in Sprint 7, the Developers may adjust the forecast for Sprint 8 based on learning. Incomplete items should be returned to the Product Backlog for reordering, ensuring prioritization aligns with goals.

Applying Scrum

Question

Based on "Sprint 7 Burn-Down Chart," would you do anything different in Sprint 8? (choose the best two answers)

Options

  • AThe Developers may forecast less overall work in Sprint 8.
  • BStakeholders will encourage the Scrum Team to estimate better during the Sprint 8 Planning
  • CThere is nothing wrong. The Developers will present all Product Backlog items selected for Sprint
  • DThe Developers carry over incomplete Sprint Backlog items from Sprint 7 to Sprint 8 and monitor
  • EThe Scrum Master adds additional Developers for Sprint 8.
  • FThe Developers put incomplete Product Backlog items back into the Product Backlog for re-

How the community answered

(27 responses)
  • A
    56% (15)
  • B
    4% (1)
  • C
    7% (2)
  • D
    11% (3)
  • E
    22% (6)

Explanation

If a burn-down chart shows issues in Sprint 7, the Developers may adjust the forecast for Sprint 8 based on learning. Incomplete items should be returned to the Product Backlog for reordering, ensuring prioritization aligns with goals.

Topics

#burn-down chart#Sprint adaptation#Product Backlog#forecasting