PSD · Question #158

When does a Sprint conclude? (choose the best answer)

The correct answer is B. When the Sprint Retrospective is complete.. The Sprint officially concludes when the Sprint Retrospective is complete. This marks the end of the timebox, ensuring continuous improvement for the next Sprint.

Applying Scrum

Question

When does a Sprint conclude? (choose the best answer)

Options

  • AWhen all the tasks are completed by the Developers.
  • BWhen the Sprint Retrospective is complete.
  • CWhen all Product Backlog items meet their Definition of Done.
  • DWhen the Product Owner decides enough has been delivered to meet the Sprint Goal.

How the community answered

(52 responses)
  • B
    94% (49)
  • C
    2% (1)
  • D
    4% (2)

Explanation

The Sprint officially concludes when the Sprint Retrospective is complete. This marks the end of the timebox, ensuring continuous improvement for the next Sprint.

Topics

#Sprint events#Sprint Retrospective#timebox#Sprint conclusion