Scrum
PSD · Question #147
PSD Question #147: Real Exam Question with Answer & Explanation
The correct answer is A. The Scrum Team has all the skills to create an Increment by the end of every Sprint.. A cross-functional Scrum Team possesses all the necessary skills within the team to deliver a Done Increment at the end of each Sprint. This ensures no external dependencies for completion.
Question
How do you know that a Scrum Team is cross-functional? (choose the best answer)
Options
- AThe Scrum Team has all the skills to create an Increment by the end of every Sprint.
- BEvery member of the Scrum Team is able to perform every task.
- CThere are no conflicts within the Scrum Team.
- DA few of the Developers pair program and do Test-Driven Development.
Explanation
A cross-functional Scrum Team possesses all the necessary skills within the team to deliver a Done Increment at the end of each Sprint. This ensures no external dependencies for completion.
Community Discussion
No community discussion yet for this question.