The correct answer is D. The Developers.. The Developers own the Sprint Backlog as it represents their plan for achieving the Sprint Goal. They update it throughout the Sprint to reflect their progress.
Question
Who owns the Sprint Backlog? (choose the best answer)
Options
- AThe Product Owner.
- BThe Scrum Team.
- CThe Scrum Master.
- DThe Developers.
Explanation
The Developers own the Sprint Backlog as it represents their plan for achieving the Sprint Goal. They update it throughout the Sprint to reflect their progress.