PSD · Question #142
PSD Question #142: Real Exam Question with Answer & Explanation
The correct answer is B. False. Scrum does not have a concept of a "Release Sprint." Each Sprint must result in a Done Increment, which may be released as required. The focus is on continuous delivery of value, not specific release cycles.
Question
True or False: A high-performance Scrum Team ensures that each Increment is complete by running a Release Sprint.
Options
- ATrue
- BFalse
Explanation
Scrum does not have a concept of a "Release Sprint." Each Sprint must result in a Done Increment, which may be released as required. The focus is on continuous delivery of value, not specific release cycles.