PSD · Question #134

What activities would a Product Owner typically undertake in the phase between the end of the current sprint and the start of the next sprint?

The correct answer is D. There are no such activities. The next sprint starts immediately after the current sprint. There is no time in between sprints, so there cannot be activities.

Applying Scrum

Question

What activities would a Product Owner typically undertake in the phase between the end of the current sprint and the start of the next sprint?

Options

  • AWork with the QA departments on the increment of the current sprint
  • BUpdate the project plan with stakeholders
  • CRefine the backlog
  • DThere are no such activities. The next sprint starts immediately after the current sprint

How the community answered

(39 responses)
  • A
    5% (2)
  • C
    3% (1)
  • D
    92% (36)

Explanation

There is no time in between sprints, so there cannot be activities.

Topics

#sprint transition#sprint cadence#backlog refinement