Which three of the following are feedback loops in scrum?

The correct answer is B. Daily scrum C. Sprint review D. Sprint retrospective. Refinement meeting and release planing are no scrum events. The others are, and they are all about feedback: inspection and adaptation. (And in order for the inspection to have a good outcome, the artifacts need to be transparent)

Applying Scrum

Question

Which three of the following are feedback loops in scrum?

Options

  • ARelease planning
  • BDaily scrum
  • CSprint review
  • DSprint retrospective
  • ERefinement meeting

How the community answered

(13 responses)
  • A
    8% (1)
  • B
    92% (12)

Explanation

Refinement meeting and release planing are no scrum events. The others are, and they are all about feedback: inspection and adaptation. (And in order for the inspection to have a good outcome, the artifacts need to be transparent)