PSD · Question #125

What are the developers responsible for? (choose two)

The correct answer is A. Resolving conflicts amongst the developers C. Organizing work required to meet the sprint goal. They are concerned with everything that needs to happen to create a working increment. And they are self-managing, so resolving conflicts is something they should arrange as well.

Applying Scrum

Question

What are the developers responsible for? (choose two)

Options

  • AResolving conflicts amongst the developers
  • BSelecting the product owner
  • COrganizing work required to meet the sprint goal
  • DReporting productivity

How the community answered

(15 responses)
  • A
    87% (13)
  • B
    7% (1)
  • D
    7% (1)

Explanation

They are concerned with everything that needs to happen to create a working increment. And they are self-managing, so resolving conflicts is something they should arrange as well.

Topics

#developer responsibilities#sprint goal#self-management#conflict resolution