PSD · Question #108

What is a sprint burn down chart?

The correct answer is A. Visual representation of work that is still to do and time that is left. You've hit your limit · resets 5am (America/New_York)

Applying Scrum

Question

What is a sprint burn down chart?

Options

  • AVisual representation of work that is still to do and time that is left
  • BA chart showing progress towards the product goal
  • CA chart that shows whether bugs came up
  • DVisual representation of the product backlog items left

How the community answered

(37 responses)
  • A
    92% (34)
  • B
    5% (2)
  • D
    3% (1)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#sprint burndown#sprint progress#scrum artifacts