PSD · Question #105
When more teams are working on the same product. How should they go about their definition of done?
The correct answer is C. All development teams must have a DoD that makes their combined work releasable.. The product must be releasable and done must mean the same for all additions to the product. So they must have a DoD that can combined. There is no hardening sprint.
Applying Scrum
Question
When more teams are working on the same product. How should they go about their definition of done?
Options
- AEvery team must make their own DoD, a meeting should be organised so that the differences are
- BIt depends on the product owner
- CAll development teams must have a DoD that makes their combined work releasable.
- DEvery team uses its own. The differences are discussed in a hardening sprint.
How the community answered
(26 responses)- A4% (1)
- B12% (3)
- C81% (21)
- D4% (1)
Explanation
The product must be releasable and done must mean the same for all additions to the product. So they must have a DoD that can combined. There is no hardening sprint.
Topics
#definition of done#multiple teams#scaled scrum