PSD · Question #103

PSD Question #103: Real Exam Question with Answer & Explanation

The correct answer is C. The Sprint goal. Review the scrum guide section sprint planning if this is still an uncertainty for you.

Question

Which output from sprint planning provides the developers with a target and overarching direction for the sprint?

Options

  • AThe sprint backlog
  • BThe product goal
  • CThe Sprint goal
  • DSprint review minutes

Explanation

Review the scrum guide section sprint planning if this is still an uncertainty for you.