The correct answer is C. The Sprint goal. Review the scrum guide section sprint planning if this is still an uncertainty for you.
Question
Which output from sprint planning provides the developers with a target and overarching direction for the sprint?
Options
- AThe sprint backlog
- BThe product goal
- CThe Sprint goal
- DSprint review minutes
Explanation
Review the scrum guide section sprint planning if this is still an uncertainty for you.