PRINCE2-FOUNDATION Exam Questions
1,059 real PRINCE2-FOUNDATION exam questions with expert-verified answers and explanations. Page 14 of 22.
- Question #657
Which is a purpose of the Controlling a Stage process?
- Question #658
Which defines the sequence in which the products of a plan should be developed?
- Question #659
If a Work Package is forecast to exceed its tolerances, how should a Team Manager inform the Project Manager?
- Question #660
What process enables an organization to understand the work that needs to be done to deliver a project's products before it is approved?
- Question #661
Which is a responsibility of the Project Assurance role?
- Question #662
When is it confirmed if a project's objectives have been achieved?
- Question #663
Which is a definition of a risk cause?
- Question #664
When would the Team Manager be required to produce a Checkpoint Report?
- Question #665
Which is a recommended quality review team role?
- Question #666
In what product would a product's quality tolerance be defined?
- Question #667
When should the Managing a Stage Boundary process be undertaken?
- Question #668
What principle is supported by the Project Product Description?
- Question #669
Which is a definition of risk probability?
- Question #670
Identify the missing words in the following sentence. The Project Board will allocate tolerances [ ? ] to the Project Manager.
- Question #671
Which is NOT a purpose of a Product Description?
- Question #672
Which is a purpose of a Communication Management Strategy?
- Question #673
Identify the missing word(s) from the following sentence. A project is a temporary organization that is created for the purpose of delivering one or more business products accordin...
- Question #674
According to PRINCE2, which of the following is a characteristic of a project compared to that of business operations?
- Question #675
Which of the following is FALSE?
- Question #676
According to PRINCE2, which of the following are the aspects of project performance to be managed?
- Question #678
A characteristic of a project is that they come with an element of uncertainty. Which of the following PRINCE2 themes will help with the identification and management of such uncer...
- Question #679
Which is a benefit of using PRINCE2?
- Question #680
Which PRINCE2 principle supports planning only to a level of detail that is manageable and foreseeable?
- Question #681
Which is NOT a PRINCE2 integrated element?
- Question #682
Which is a characteristic of a project?
- Question #683
Which is one of the six aspects of project performance that needs to be managed?
- Question #684
Identify the missing words in the following sentence... A principle of PRINCE2 is that a project has defined and agreed?
- Question #685
Identify the missing words in the following sentence... A PRINCE2 project is and controlled on a stage-by-stage basis?
- Question #686
Identify the missing word in the following sentence... A PRINCE2 project has defined for each project objective to establish limits of delegated authority?
- Question #687
The purpose of the Progress theme is to do which of the following?
- Question #688
Which of the following statements are correct regarding the use of management stages? 1. Provide review and decision points 2. Enable key decisions to be made prior to the detailed...
- Question #689
Which of the following are correct regarding the definition of a technical stage? 1. Technical stages never overlap 2. They are typified by the use of a particular set of specialis...
- Question #690
Which of the following are factors that need to be taken into consideration when identifying management stages? 1. Where the key decisions points need to be 2. The amount of risk w...
- Question #691
The creation of an Exception Plan often follows which of the following situations?
- Question #692
What type of progress control is a Checkpoint Report?
- Question #693
Which of the following is NOT within the authority of the Project Board?
- Question #694
Which of the following is a Project Board control?
- Question #695
Which level of management in the project management team has the ability to review progress and decide whether to continue, change or stop the project?
- Question #696
There should be at least two management stages in a PRINCE2 project. Which of the following options describes those stages?
- Question #697
Which process is predicated on dividing the project into management stages?
- Question #698
Which of the following products are routinely produced as part of the Managing a Stage Boundary process? 1. Next Stage Plan 2. Updated Project Plan 3. Exception Plan 4. Updated Bus...
- Question #699
Which of the following is a purpose of the Managing a Stage Boundary process?
- Question #700
Which process has a specific objective to ensure there is business justification for initiating the project?
- Question #701
Please refer to section 12.2 in the PRINCE2 Manual. (The initiation Stage Plan is produced in the Starting up a Project process and is then used by the Project Board to authorize t...
- Question #702
Which process is largely about preventing poorly conceived projects from ever being initiated?
- Question #703
Which of the following, produced in the Starting Up a Project process, defines the way the project is to be delivered after evaluating the various delivery methods?
- Question #704
Which of the following would be defined within the Project Brief?
- Question #705
Which product acts as a trigger for the Starting Up a Project process?
- Question #706
Which of the following would be carried out during the Starting Up a Project process?
- Question #707
Which is a purpose of the Starting up a Project process?