PRINCE2-FOUNDATION · Question #704

Which of the following would be defined within the Project Brief?

The correct answer is B. The scope of the project. See the full explanation below for the reasoning.

Question

Which of the following would be defined within the Project Brief?

Options

  • AThe Communication Management Strategy
  • BThe scope of the project
  • CThe initiation Stage Plan
  • DThe Lessons Report for the project

How the community answered

(50 responses)
  • A
    14% (7)
  • B
    76% (38)
  • C
    8% (4)
  • D
    2% (1)