PRINCE2-FOUNDATION · Question #662

When is it confirmed if a project's objectives have been achieved?

The correct answer is A. During the Closing a Project process. See the full explanation below for the reasoning.

Question

When is it confirmed if a project's objectives have been achieved?

Options

  • ADuring the Closing a Project process
  • BDuring the final end stage assessment
  • CDuring the Controlling a Stage process
  • DDuring the Managing Product Delivery process

How the community answered

(33 responses)
  • A
    82% (27)
  • B
    3% (1)
  • C
    6% (2)
  • D
    9% (3)