PRINCE2-FOUNDATION · Question #659
If a Work Package is forecast to exceed its tolerances, how should a Team Manager inform the Project Manager?
The correct answer is C. Raise an issue. See the full explanation below for the reasoning.
Question
If a Work Package is forecast to exceed its tolerances, how should a Team Manager inform the Project Manager?
Options
- ARaise an Exception Report
- BIssue an Exception Plan
- CRaise an issue
- DRaise a risk
How the community answered
(18 responses)- A11% (2)
- B6% (1)
- C78% (14)
- D6% (1)