If a Work Package is forecast to exceed its tolerances, how should a Team Manager inform the Project Manager?

The correct answer is C. Raise an issue. See the full explanation below for the reasoning.

Question

If a Work Package is forecast to exceed its tolerances, how should a Team Manager inform the Project Manager?

Options

  • ARaise an Exception Report
  • BIssue an Exception Plan
  • CRaise an issue
  • DRaise a risk

How the community answered

(18 responses)
  • A
    11% (2)
  • B
    6% (1)
  • C
    78% (14)
  • D
    6% (1)

Community Discussion

No community discussion yet for this question.