PeopleCert
PRINCE2-FOUNDATION · Question #659
PRINCE2-FOUNDATION Question #659: Real Exam Question with Answer & Explanation
Sign in or unlock PRINCE2-FOUNDATION to reveal the answer and full explanation for question #659. The question stem and answer options stay visible for context.
Question
If a Work Package is forecast to exceed its tolerances, how should a Team Manager inform the Project Manager?
Options
- ARaise an Exception Report
- BIssue an Exception Plan
- CRaise an issue
- DRaise a risk
Unlock PRINCE2-FOUNDATION to see the answer
You've previewed enough free PRINCE2-FOUNDATION questions. Unlock PRINCE2-FOUNDATION for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.