Which of the following is NOT within the authority of the Project Board?

The correct answer is D. Set project-level tolerance. See the full explanation below for the reasoning.

Question

Which of the following is NOT within the authority of the Project Board?

Options

  • AApprove the End Project Report
  • BSet Stage-level tolerance
  • CApprove Stage Plans
  • DSet project-level tolerance

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    13% (4)
  • C
    10% (3)
  • D
    74% (23)