nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #694

Which of the following is a Project Board control?

The correct answer is B. Stage-level tolerance. See the full explanation below for the reasoning.

Question

Which of the following is a Project Board control?

Options

  • AProject-level tolerance
  • BStage-level tolerance
  • CCheckpoint Report
  • DQuality Register

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    77% (27)
  • C
    3% (1)
  • D
    14% (5)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice