PRINCE2-FOUNDATION · Question #694
Which of the following is a Project Board control?
The correct answer is B. Stage-level tolerance. See the full explanation below for the reasoning.
Question
Which of the following is a Project Board control?
Options
- AProject-level tolerance
- BStage-level tolerance
- CCheckpoint Report
- DQuality Register
How the community answered
(35 responses)- A6% (2)
- B77% (27)
- C3% (1)
- D14% (5)