PRINCE2-FOUNDATION · Question #988

PRINCE2-FOUNDATION Question #988: Real Exam Question with Answer & Explanation

The correct answer is D. It allows the project team to identify improvements to be made during the project. See the full explanation below for the reasoning.

Question

What is an advantage of applying the 'learn from experience' principle?

Options

  • AIt allows the project board to delegate cost tolerances to the project manager
  • BIt allows the project team to fully understand their roles and responsibilities
  • CIt allows the project manager to delegate time tolerances to the team managers
  • DIt allows the project team to identify improvements to be made during the project