PRINCE2-FOUNDATION · Question #987

As a minimum requirement for applying the risk theme, what must specifically be assessed?

The correct answer is D. Whether a risk may alter the project's business justification. See the full explanation below for the reasoning.

Question

As a minimum requirement for applying the risk theme, what must specifically be assessed?

Options

  • AWhether a risk may cause the project to exceed its cost tolerance
  • BWhether a risk may affect the project-level quality tolerances
  • CWhether a risk may impact the underlying technical assumptions
  • DWhether a risk may alter the project's business justification

How the community answered

(45 responses)
  • A
    4% (2)
  • B
    9% (4)
  • C
    13% (6)
  • D
    73% (33)