PeopleCert
PRINCE2-FOUNDATION · Question #987
As a minimum requirement for applying the risk theme, what must specifically be assessed?
The correct answer is D. Whether a risk may alter the project's business justification. See the full explanation below for the reasoning.
Question
As a minimum requirement for applying the risk theme, what must specifically be assessed?
Options
- AWhether a risk may cause the project to exceed its cost tolerance
- BWhether a risk may affect the project-level quality tolerances
- CWhether a risk may impact the underlying technical assumptions
- DWhether a risk may alter the project's business justification
How the community answered
(45 responses)- A4% (2)
- B9% (4)
- C13% (6)
- D73% (33)