PRINCE2-FOUNDATION · Question #989

PRINCE2-FOUNDATION Question #989: Real Exam Question with Answer & Explanation

The correct answer is C. To estimate the risk to the project in terms of probability and impact. See the full explanation below for the reasoning.

Question

What is a goal of the 'implement' step within the recommended risk management procedure?

Options

  • ATo prepare specific management responses to identified risks
  • BTo monitor the effectiveness of actioned risk responses
  • CTo estimate the risk to the project in terms of probability and impact
  • DTo communicate information related to the risks faced by the project