What is a goal of the 'implement' step within the recommended risk management procedure?

The correct answer is C. To estimate the risk to the project in terms of probability and impact. See the full explanation below for the reasoning.

Question

What is a goal of the 'implement' step within the recommended risk management procedure?

Options

  • ATo prepare specific management responses to identified risks
  • BTo monitor the effectiveness of actioned risk responses
  • CTo estimate the risk to the project in terms of probability and impact
  • DTo communicate information related to the risks faced by the project

How the community answered

(51 responses)
  • A
    10% (5)
  • B
    2% (1)
  • C
    82% (42)
  • D
    6% (3)