PRINCE2-FOUNDATION · Question #86
Which Process is used to design the Project Management Team?
The correct answer is C. Starting Up a Project. See the full explanation below for the reasoning.
Question
Which Process is used to design the Project Management Team?
Options
- AInitiating a Project
- BAuthorising a Project
- CStarting Up a Project
- DDirecting a Project
How the community answered
(47 responses)- A13% (6)
- B6% (3)
- C77% (36)
- D4% (2)