Which of the following is NOT a step in PRINCE2 Risk Management?

The correct answer is B. Risk budget. See the full explanation below for the reasoning.

Question

Which of the following is NOT a step in PRINCE2 Risk Management?

Options

  • AAssess
  • BRisk budget
  • CIdentify
  • DImplement

How the community answered

(62 responses)
  • A
    11% (7)
  • B
    81% (50)
  • C
    5% (3)
  • D
    3% (2)