Which of the following is not an objective of the process Initiating a Project?

The correct answer is D. It ensures that all project management authorities are appointed. See the full explanation below for the reasoning.

Question

Which of the following is not an objective of the process Initiating a Project?

Options

  • AIt encourages the Project Board to take ownership of the project
  • BIt provides the benchmark for decision-making processes throughout the projects life
  • CIt confirms the existence of an acceptable Business Case justifying the project
  • DIt ensures that all project management authorities are appointed

How the community answered

(49 responses)
  • A
    4% (2)
  • B
    10% (5)
  • C
    16% (8)
  • D
    69% (34)