Which of the following is a trigger for the Project Manager to update the Stage Plan with actuals?

The correct answer is B. Receipt of a Checkpoint Report from a team manager. See the full explanation below for the reasoning.

Question

Which of the following is a trigger for the Project Manager to update the Stage Plan with actuals?

Options

  • AOnce agreed, the Stage Plan never gets updated
  • BReceipt of a Checkpoint Report from a team manager
  • CReceipt of a Project Issue
  • DAn entry made into the daily log

How the community answered

(30 responses)
  • A
    7% (2)
  • B
    80% (24)
  • C
    10% (3)
  • D
    3% (1)