Which of the following is a trigger for the Project Manager to update the Stage Plan with actuals?
The correct answer is B. Receipt of a Checkpoint Report from a team manager. See the full explanation below for the reasoning.
Question
Which of the following is a trigger for the Project Manager to update the Stage Plan with actuals?
Options
- AOnce agreed, the Stage Plan never gets updated
- BReceipt of a Checkpoint Report from a team manager
- CReceipt of a Project Issue
- DAn entry made into the daily log
How the community answered
(30 responses)- A7% (2)
- B80% (24)
- C10% (3)
- D3% (1)