nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #81

Which of the following are produced during the Starting Up a Project stage?

The correct answer is D. Project Brief. See the full explanation below for the reasoning.

Question

Which of the following are produced during the Starting Up a Project stage?

Options

  • AProject Plan
  • BProject Initiation Document
  • CProject Quality Plan
  • DProject Brief

How the community answered

(66 responses)
  • A
    3% (2)
  • B
    15% (10)
  • C
    8% (5)
  • D
    74% (49)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice