PeopleCert
PRINCE2-FOUNDATION · Question #80
Which of the following is an in put to the "Plan the Next Stage" activity in the "Managing a Stage Boundary" process?
The correct answer is A. Issue Register. See the full explanation below for the reasoning.
Question
Which of the following is an in put to the “Plan the Next Stage” activity in the “Managing a Stage Boundary” process?
Options
- AIssue Register
- BCheckpoint Report
- CProject Product Descriptions
- DException Plan
How the community answered
(44 responses)- A75% (33)
- B9% (4)
- C2% (1)
- D14% (6)
Community Discussion
No community discussion yet for this question.