PRINCE2-FOUNDATION · Question #79

Which of the following does not aid the Project Manager in exerting control?

The correct answer is A. Project Initiation Documentation. See the full explanation below for the reasoning.

Question

Which of the following does not aid the Project Manager in exerting control?

Options

  • AProject Initiation Documentation
  • BWork Package
  • CException Plan
  • DProject Plan

How the community answered

(24 responses)
  • A
    79% (19)
  • B
    4% (1)
  • C
    4% (1)
  • D
    13% (3)