At which point does the PRINCE2 Project Board carry out its first major activity?

The correct answer is A. After Starting up a Project. See the full explanation below for the reasoning.

Question

At which point does the PRINCE2 Project Board carry out its first major activity?

Options

  • AAfter Starting up a Project
  • BOnce corporate / programme management has given a Project Mandate
  • CAt the beginning of Starting up a Project
  • DOnce the Project Mandate has been created

How the community answered

(36 responses)
  • A
    83% (30)
  • B
    3% (1)
  • C
    8% (3)
  • D
    6% (2)