At which point does the PRINCE2 Project Board carry out its first major activity?
The correct answer is A. After Starting up a Project. See the full explanation below for the reasoning.
Question
At which point does the PRINCE2 Project Board carry out its first major activity?
Options
- AAfter Starting up a Project
- BOnce corporate / programme management has given a Project Mandate
- CAt the beginning of Starting up a Project
- DOnce the Project Mandate has been created
How the community answered
(36 responses)- A83% (30)
- B3% (1)
- C8% (3)
- D6% (2)