PRINCE2-FOUNDATION · Question #83

A Project Mandate is turned into a Project Brief by which of the following processes?

The correct answer is B. Starting Up a Project. See the full explanation below for the reasoning.

Question

A Project Mandate is turned into a Project Brief by which of the following processes?

Options

  • AManaging Product Delivery
  • BStarting Up a Project
  • CInitiating a Project
  • DAuthorising Initiation

How the community answered

(32 responses)
  • A
    6% (2)
  • B
    75% (24)
  • C
    16% (5)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.