PeopleCert
PRINCE2-FOUNDATION · Question #819
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
The correct answer is D. Checkpoint Report. See the full explanation below for the reasoning.
Question
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
Options
- AConfiguration Item Record
- BQuality Register
- CHighlight Report
- DCheckpoint Report
How the community answered
(38 responses)- A8% (3)
- B3% (1)
- C5% (2)
- D84% (32)
Community Discussion