nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #819

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

The correct answer is D. Checkpoint Report. See the full explanation below for the reasoning.

Question

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

Options

  • AConfiguration Item Record
  • BQuality Register
  • CHighlight Report
  • DCheckpoint Report

How the community answered

(38 responses)
  • A
    8% (3)
  • B
    3% (1)
  • C
    5% (2)
  • D
    84% (32)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice