nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #820

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

The correct answer is D. All levels of management. See the full explanation below for the reasoning.

Question

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

Options

  • AOnly corporate or programme management
  • BOnly the Project Board
  • COnly the Project Manager
  • DAll levels of management

How the community answered

(25 responses)
  • A
    12% (3)
  • B
    4% (1)
  • C
    4% (1)
  • D
    80% (20)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice