PeopleCert
PRINCE2-FOUNDATION · Question #820
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
The correct answer is D. All levels of management. See the full explanation below for the reasoning.
Question
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
Options
- AOnly corporate or programme management
- BOnly the Project Board
- COnly the Project Manager
- DAll levels of management
How the community answered
(25 responses)- A12% (3)
- B4% (1)
- C4% (1)
- D80% (20)
Community Discussion
No community discussion yet for this question.