PRINCE2-FOUNDATION · Question #818

How many management stages should a PRINCE2 project consist of?

The correct answer is C. Initiation stage and at least one other management stage to cover the remainder of the project. See the full explanation below for the reasoning.

Question

How many management stages should a PRINCE2 project consist of?

Options

  • AStart up stage, initiation stage and at least one other management stage to cover the remainder
  • BStart up stage, at least one other management stage to cover the remainder of the project and a
  • CInitiation stage and at least one other management stage to cover the remainder of the project
  • DStart up stage, initiation stage and a closing stage

How the community answered

(28 responses)
  • A
    14% (4)
  • B
    4% (1)
  • C
    75% (21)
  • D
    7% (2)