Which plan provides the Business Case with costs during the Initiating a Project process?

The correct answer is B. Project Plan. See the full explanation below for the reasoning.

Question

Which plan provides the Business Case with costs during the Initiating a Project process?

Options

  • AInitiation Stage Plan
  • BProject Plan
  • CStage Plan
  • DTeam Plan

How the community answered

(41 responses)
  • A
    17% (7)
  • B
    71% (29)
  • C
    2% (1)
  • D
    10% (4)