PRINCE2-FOUNDATION · Question #768

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

The correct answer is B. Project Initiation Documentation. See the full explanation below for the reasoning.

Question

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

Options

  • AProject Brief
  • BProject Initiation Documentation
  • CProject mandate
  • DBenefits Review Plan

How the community answered

(42 responses)
  • A
    10% (4)
  • B
    83% (35)
  • C
    5% (2)
  • D
    2% (1)