Which is NOT a purpose of the Initiating a Project process?
The correct answer is D. Enable the Project Board to decide whether it is worthwhile to initiate a project. See the full explanation below for the reasoning.
Question
Which is NOT a purpose of the Initiating a Project process?
Options
- AEnable a Project Board decision about the commitment of resources to a project
- BEnable an organization to understand the work that needs to be done to deliver a project's
- CEstablish solid foundations for a project
- DEnable the Project Board to decide whether it is worthwhile to initiate a project
How the community answered
(38 responses)- A5% (2)
- B8% (3)
- C3% (1)
- D84% (32)