PRINCE2-FOUNDATION · Question #757
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
The correct answer is C. Work Package. See the full explanation below for the reasoning.
Question
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
Options
- AProduct Description
- BTeam Plan
- CWork Package
- DStage Plan
How the community answered
(28 responses)- A4% (1)
- B7% (2)
- C75% (21)
- D14% (4)