nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #757

In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

The correct answer is C. Work Package. See the full explanation below for the reasoning.

Question

In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

Options

  • AProduct Description
  • BTeam Plan
  • CWork Package
  • DStage Plan

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    7% (2)
  • C
    75% (21)
  • D
    14% (4)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice