PRINCE2-FOUNDATION · Question #756
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
The correct answer is B. Controlling a Stage. See the full explanation below for the reasoning.
Question
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
Options
- ADirecting a Project
- BControlling a Stage
- CManaging a Stage Boundary
- DManaging Product Delivery
How the community answered
(33 responses)- A6% (2)
- B79% (26)
- C12% (4)
- D3% (1)