nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #756

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

The correct answer is B. Controlling a Stage. See the full explanation below for the reasoning.

Question

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

Options

  • ADirecting a Project
  • BControlling a Stage
  • CManaging a Stage Boundary
  • DManaging Product Delivery

How the community answered

(33 responses)
  • A
    6% (2)
  • B
    79% (26)
  • C
    12% (4)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice